What I’d do differently

You know how I said I’d never ever do something like this ever again?   And that building a house isn’t something that I’d wish on my worst enemy?

Well, I don’t feel like that any more, or at least not all the time.

I suppose the bad experiences fade and you just have the good stuff left. It’s like forgetting the hard slog, exhaustion, frozen extremities, fear and exposure, and the long slog down in the dark of a day winter mountaineering in Scotland.  Somehow, the next week when someone asks you if you want to go out to the hills, you only remember that moment when the sun burst through the mist of fog crystals on the summit, so that the air sparkled with delight, and not the hellish rest of it.

That’s not to say I’m about to build another house. No no. That is absolutely not going to happen, I’m just saying I don’t wake up in the night any more wondering why I started this thing. It’s probably a good moment to share some of the things that I would change if I were building the house again (gosh, imagine what a nightmare that would be? Being made to start all over again on a massive task that you’d only just survived the first time round…aaargghh)

So here we go, I don’t think this can be a definitive list, but here’s a selection.

Cladding

Over the winter I went through a phase of cringing when I saw the huge white gable of the house shining like a beacon across the bay.

I’d really wanted that whole main section of the house and gable to be clad in larch, which would fade to silver grey and blend with the hillside but the planners wanted the main part of the house to be harled in white. Going back further our plan was to have the whole house clad in larch, but it was clear from planning that a combination of wood and harling would be more acceptable. We ended up switching the harled and clad sections over, reducing the area of wood cladding to about a third of the area of the house.

Half way through building, when I was having that terrible nightmare finding a company to do the cladding and I found out that the harled cladding system was going to cost around twice the price of the wood cladding, I wished we had pressed the case for wood cladding harder. When the house was complete and the scaffolding came off, I wished it even more, especially with seeing how the wood section is starting to blend so beautifully with the surroundings.

Waiting months and months for the curtains for the huge windows downstairs and up didn’t help (and not having a ladder long enough to actually put them up). In the absence of other things to fret about, I worried about how my house shone like a beacon across the bay for hundreds of miles to the south.

However, now it’s summer and the trees are in full leaf, the house stands is screened from the bay and I’m starting to get used to the harling.

 

Being the proud owner of a stairwell atrium 

All the other things that annoyed me at various points in the build are getting less annoying. Even that enormous high 7.5 m stairwell which was such a pain to make airtight, plasterboard, decorate, and which I will never be able to clean the windows of, is actually quite picturesque and uplifting to live with. The omission of a light on the stairs (it really is crying out for one of those huge dangling spiral chandeliers to match the space) doesn’t bother me anymore either.

I actually noticed the lack of light early on, while we were plaster-boarding, but I was so caught in the nightmare of Phil (Builder#4) and contemplating how to sack him, that I couldn’t face the strain of liaising between him and the electrician to get it fixed.

Anyway, it’s all settling in. Though next time, in the interests of economy, I’d leave the atrium out of the house and use the space for something useful.

But don’t fear – I have a plan for that atrium. When the dust has settled and I feel I can countenance working with a builder again, I’ll build a giant shelf in the stairwell as a little tree-house/den for me. It will have a book-shelf and two bean bags, a ladder I can hoist up in case of emergency, and an amazing view through the massive window (which I would now actually be able to clean) up to the Ballachulish Horseshoe.

 

Technical blah blah: Heating system and Biodisk. 

There’s other annoying stuff like finding the heating system had two cylinders instead of one, thus taking up the space in the drying room allocated for boot racks and such.   And the biodisk septic tank having a white protuberance that sits in the middle of my garden and whirrs. Both of these irritations are down to me not asking enough questions at the start of the build and just letting things happen – the architects specified the type of biodisk, and Stuart, builder 1, recommended a local company for the heating system. I

 

I’m getting used to the low buzz of the heat pump but I still can’t work the really complicated user interface. I’m convinced someone should a have been able to invent something a bit easier to work.

Of course Stephen the builder had lots of say about how much better the heating system is in his house, as he does about almost everything else too. (For those who don’t know the whole story, Stephen came on the scene late on in the build and saved the whole caboodle from disaster – twice – however the payment from my side appears to be to have the piss taken for various bad decisions I made, and to hear how much better the house he built himself is. It’s really a small price to pay to be honest.)

I feel I was more involved in the whole MVHR and wood burning stove planning and installation and I’m much happier with how they work (despite the little hole-drilling mishap).

We moved the MVHR exit and intake from the roof to out the back and that works really well. It means you can’t see it and It’s also on the north side of the house so when it’s warm in the house, it provides quite an effective method of cooling (not as effective as opening the doors and windows of course….).

Shape and Space. 

It only occurred to me once the house was built that having a 1m x 2m sticky-out bit at the back of the house, that allows for the turn of the staircase, was a rather inefficient use of space. Given the extra difficulties of making the house the shape it is at the back, with a complex roof arrangement, it’s likely that it would actually have been cheaper to make the house an extra metre bigger all across the back, which would also mean I’d have a bigger hall to throw my muddy wellies around in.

And, if I’m feeling extra picky. I’d have left an extra 50cm at the front of the house. So I could walk all round the dining table without having to squeeeeze past the chairs. (but that’s being unreasonably picky, to be honest).

 

Paying attention

Another thing that happened because I wasn’t quite ‘on it’ at the start of the build was cold bridging under the doors. If I was building a house again I’d be far more with it from the very beginning. I seem to have two modes of operation: lassez faire, delegating and trusting people to do their job, and control freakery. To be honest, I think I’d have put in a bit more control freakery at the start of the build to make sure everything was going to plan. I would obsessively check things; I would print out the plans hundreds of time and distribute them to absolutely everyone, irritating them by pointing out things that were obvious to them already.

If I’d have done this then I wouldn’t have a 200mm section of breeze blocks right under the wood floor on the thresholds into the house. The architects had a plan that had the breeze block foundation dropping down where the patio doors were to allow for some insulation to prevent cold bridging. It wasn’t immediately clear to me from the diagrams and it was actually only when I felt the cold coming up from the floor by the patio doors, once the whole house was finished that I placed the cross sections side by side and worked out what was supposed to have happened.

 

It is a little frustrating that I did actually pay for one site visit for the architects after I took over project management and it was at the point the timber kit had gone up. There had been a hiatus in the work while I scrabbled about for a builder to do the cladding, having been let down by the framing company. Stephen had just taken on the job and had pointed out that the windows were in the wrong positions and would need taking out and refitting. He was on site that day to meet the architect, and I’d asked Matt whether there was anything else wrong that we should sort out. He was standing right by the patio doors when he’d said, the rest looked ok.

For the patio doors in the siting room, which I found I wasn’t using at all, Stephen and I decided to just put in some kingspan and an extra windowsill on the threshold and convert it from doors to a window. The other one, I’ll live with.

 

The Final Item in this list, decision making, is a biggie and I think I will leave it til the next blog.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s